How to Read a Stainless Steel Pipe Mill Test Certificate (MTC)

Stainless steel pipes are often accompanied by a Mill Test Certificate (MTC, also known as Manufacturer’s Test Certificate) when leaving the factory. This is a key document that guarantees material composition, mechanical properties, and traceability. For purchasing, inspection, and project acceptance personnel, mastering how to quickly and accurately read an MTC is crucial. Below is a detailed analysis and practical guidelines from multiple perspectives to facilitate use and review in actual projects.

Basic Functions and Types of MTC

The main function of an MTC is to prove that the product meets procurement specifications and relevant standards. Common types, classified by certification depth, include:

  1. Declaratory type (e.g., EN 10204 2.2): A manufacturer’s declaration and inspection results without third-party certification.
  2. Inspection certificate (e.g., EN 10204 3.1): Issued and signed by the manufacturer’s technical responsible person based on inspection records, applicable to most projects.
  3. Third-party verification (e.g., EN 10204 3.2): Signed by an independent inspection agency or a buyer-authorized inspector, applicable to high-risk or export projects.

Key Items to Check in the Certificate

  1. Manufacturer and certificate number: Confirm the issuing entity, address, certificate number, and date for easy traceability.
  2. Purchase order number/contract number/customer information: Verify consistency with the procurement contract to avoid incorrect goods.
  3. Heat number/Batch number: These are key fields for tracing materials back to the smelting batch. All chemical and mechanical data are usually based on the heat number.
  4. Product description: Information such as specifications (outer diameter, wall thickness, length), product type (e.g., seamless, welded), dimensional tolerances, and surface treatment should match the physical product and order.
  5. Applicable standards and grades: For example, ASTM A312, EN 10217, JIS, etc., specifying the standard clauses that the pipe should meet.
  6. Chemical composition table: Lists the contents of elements such as C, Si, Mn, P, S, Cr, Ni, and Mo. Check if key elements (e.g., Cr, Ni, Mo) meet contract or standard requirements. Note whether allowable deviations or ranges are indicated.
  7. Mechanical properties: Tensile strength, yield strength, elongation, etc.; impact values or low-temperature impact test results (especially important for low-temperature applications) are also listed if available.
  8. Inspection and test records: Including hydrostatic, flattening, torsion, hardness, metallographic, and welding defect detection (UT/RT) tests. Clearly check the inspection methods and acceptance criteria.
  9. NDT results: Whether non-destructive testing (UT, RT, PT, MT) is “qualified”; if there are unqualified items, there should be handling records and judgments.
  10. Additional tests: Such as nickel/chromium content detection (PMI), salt spray, and corrosion resistance tests, etc., to be verified according to contract requirements.
  11. Signatures and seals: Signatures of inspectors/quality managers, dates, and seals of inspection laboratories or third-party institutions are important identifiers of the certificate’s validity.

Verification Process (Practical Suggestions)

  1. Initial inspection and comparison: After receiving the goods, first check the appearance, dimensions, and heat number against the certificate, then conduct sampling inspection after confirmation.
  2. Chemical and mechanical spot checks: Re-inspect key batches (chemical analysis or PMI, tensile tests), especially for pipes used in pressure vessels, food, pharmaceuticals, or marine environments.
  3. Pay attention to “scope/remarks”: Remarks at the end of the certificate often contain important information, such as whether it is in a heat-treated state, special delivery conditions, or deviation explanations.
  4. Compare with standard clauses: When inspection methods or acceptance criteria in the certificate are unclear, refer to the latest standard clauses specified in the contract for comparison.

Common Issues and Red Flags

  1. Missing heat number or inconsistency with the physical product: Immediately stop use and trace back.
  2. Chemical composition close to the lower limit or missing key elements: Further laboratory testing is required for confirmation.
  3. Unperformed NDT items or missing results: Request supplementary test reports or third-party re-inspection.
  4. Certificate is declaratory but the project requires third-party verification: Request EN 10204 3.1/3.2.

Checklist for Purchasers and Supervisors (Simplified Version)

  1. Whether the certificate type meets the contract (2.2/3.1/3.2)
  2. Manufacturer name, certificate number, and date
  3. Consistency between heat number and product label
  4. Chemical composition and mechanical properties meet standards/contract
  5. Complete and qualified NDT and special test records
  6. Signatures, seals, and third-party certification (if required)

Conclusion

Reading a stainless steel pipe MTC is the first step to ensuring material safety and project quality. By systematically checking key items in the certificate, combining sampling re-inspections, and comparing with contract standards, quality risks can be significantly reduced. Adopting the above verification processes and checklists as regular steps will make your procurement and quality control more reliable and traceable in the long run.

 